Indian Pass dune restoration to begin soon

In about three weeks, work is expected to begin on a large-scale
dune restoration project along the Indian Pass peninsula, which could last as
long as five months.

That will be followed by about four months of work in the
St. Joe Beach-Beacon Hill area doing much the same thing, recreating the front
dunes that were devastated three years ago by Hurricane Michael.

County Engineer Clay Smallwood said because it is not a
massive beach renourishment, the inconvenience of homeowners should be minimal
and brief.





“That should only be in the work zone, as the contractor
will rope off that little zone as the contractor moves down the beach,” he said,
noting that while typical beach renourishment, which can involve as much as 1 million
cubic yards of sand dredged from offshore, is designed to widen an existing beach,
this project has a different goal in mind.

“They’re not doing that, they are re-creating that frontal
dune, up at the dune line,” Smallwood said. “It’s a different goal. This is to
protect the infrastructure from a five-year storm event.”

Homeowners, however, can expect noise, especially when their
portion of the beach is being worked on.

“The beach will be an ‘active construction’ site that will
take place seven days a week during daylight hours only,” reads the www.sjpbeach.com website that provides a
wealth of documents pertaining to the work.

“Off-road dump-trucks, bulldozers, front-end loaders and
other large pieces of equipment will be used in the construction of the beach
project,” it reads “You will be able to tell there is an ‘active construction’
site in your area when the operations are near or seaward of your property.”

The Federal Emergency Management Agency is funding nearly
all of the $9.3 million contract that Inland Construction and Engineering, out
of Panama City, has secured to complete Phase 1 – encompassing the natural
beaches of Indian Pass and St. Joe Beach – of FEMA’s planned Gulf County berm
work.

Phase 2 has not yet been bid, and that will be for an engineered
beach on the peninsula, north of Rish Park, that had previously been authorized
for nourishment and maintenance by the U.S. Army Corps of Engineers and the
Florida Department of Environmental Protection.

Smallwood said an area on the west end of the Cape, near Salinas
Park, has been designated by Inland as a staging area for trucking in about
300,000 cubic yards of white beach compatible sand from the Honeyville Sand
Mine in Wewahitchka.

“His plan is to start at the western end and work east to Money
Bayou and the boat ramp,” said Smallwood.

Because mobilization costs associated with pumping in
dredged sand from offshore can ran as much as $1 million, Inland is opting to
truck in the sand from Honeyville.

“It doesn’t always make sense to dredge from an offshore
site,” Smallwood said. “It’s not close and convenient to get all the way with a
fully loaded barge. It makes more sense from upland.

“We spent quite a bit of money doing a geotechnical investigation
at the Honeyville pit,” he said.

Smallwood said the work, once completed, will resemble what
has already been completed at Mexico Beach.

On the website, the county stresses that while the work will
not prevent typical activities by homeowners and renters, and the beach will
remain open, “some safety restrictions around the ‘active construction’ site
will limit access to the general public.”

“This will be a fast-moving project, so at this time we
cannot predict where and when the crews will be working and if it will impact
your property during a given week,” it reads.

The work will generally not require the taking down of dune
walkovers. “It will depend whether or not the dune fronting your property has
been eroded and will be restored during this project,” reads the website. “Whether
you remove your dune walkover before the project begins is up to you.

“When the contractor encounters any structure that is not
removed (dune walkover, gazebos, etc.) they will only place sand up to and
around it. If you leave a structure intact and the contractor places sand
around it, it may not be as much sand as your property would have received if
you had removed it,” it notes.

As part of the dune restoration project, the replanting of
the dunes will be undertaken shortly after construction. The contractor plans
on four different native species of plants – sea oats, bitter/beach-panicum, beach
elder, and gulf bluestem – selected after consulting with the US Fish and
Wildlife Service.



Meet the Editor

David Adlerstein, The Apalachicola Times’ digital editor, started with the news outlet in January 2002 as a reporter.

Prior to then, David Adlerstein began as a newspaperman with a small Boston weekly, after graduating magna cum laude from Brandeis University in Waltham, Massachusetts. He later edited the weekly Bellville Times, and as business reporter for the daily Marion Star, both not far from his hometown of Columbus, Ohio.

In 1995, he moved to South Florida, and worked as a business reporter and editor of Medical Business newspaper. In Jan. 2002, he began with the Apalachicola Times, first as reporter and later as editor, and in Oct. 2020, also began editing the Port St. Joe Star.

Wendy Weitzel The Star Digital Editor

Leave a Reply

Your email address will not be published. Required fields are marked *

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.